2026

10-Year
Assessment

Major projects update

Ozaukee County, DIC, New Substations 

The Ozaukee County Distribution Interconnection Project is to reliably serve a new load addition within the city of Port Washington, Ozaukee County, Wisconsin.  

The proposed preferred alternative includes:
  • Decker Substation – New 345-kV breaker-and-a-half interconnection substation with a +/- 350 Mvar STATCOM, capacitor banks, and E-STATCOM. For the E-STATCOM, all costs associated with the device, its acquisition, installation, and operation, will be direct-assigned to the end-use customer. 
  • Sheboygan River Substation – New 345-kV breaker-and-a-half substation. 
  • Mullet River Junction Substation – New 345-kV breaker-and-a-half substation with 500 MVA 345/138 kV transformer. 
  • Cedar Creek Junction Substation – New 345-kV breaker-and-a-half substation with 500 MVA 345/138 kV transformer. 
  • Adell Substation – New 138-kV breaker-and-a-half substation. 
  • Network the existing Edgewater – Saukville 345 kV line into the Decker Substation  
  • Network the existing South Fond du Lac – Edgewater and Cypress – Arcadian 345kV lines into the Sheboygan River Substation. 
  • Network the existing Sheboygan Energy Center – Granville, South Fond du Lac – Edgewater, and Edgewater – Saukville 345 kV lines into the Mullet River Junction Substation. 
  • Network the existing Cypress – Arcadian and Sheboygan Energy Center – Granville 345kV lines into the Cedar Creek Junction Substation. 
  • Network the existing Plymouth 5 – Saukville (Cedarsauk) and Lyndon – Fredonia 138 kV lines into the new Adell Substation. 
  • Constructing new Mullet River Junction – Decker – Cedar Creek Junction 345 kV line by removing segments of the existing Edgewater – Saukville (Cedarsauk), Plymouth 4 – Holland – Saukville (Cedarsauk) double circuit 345-138 kV lines and replacing them as a double circuit 345 kV lines, and also converting Barton – Saukville (Cedarsauk) 138 kV line to 345 kV.  
  • Construct a new Forest Junction – Sheboygan River 345 kV line by rebuilding segments of an existing 345 kV line as double-circuits. 
  • Construc two new Adell – Holland 138 kV lines 
  • Restore the network connection to the 138 kV lines to Plymouth 4 and Barton substations by reconnecting lines at the Mullet River Junction and Cedar Creek Junction substations. 
  • Uprate the newly established and existing transmission lines. 

The target in-service date of this project is 17 months after receipt of  Certificate of Public Convenience and Necessity (CPCN) application approval. The CPCN application has been resubmitted to PSCW in September 2026, and it has been reviewed and approved by MISO through the Expedited Project Review (EPR) process.  

Walnut – Blount 69kV, New Line 

This project will provide a third 69 kV transmission source between West Campus generation (Walnut Substation) and Blount Substation in downtown Madison, utilizing existing vacant infrastructure. The proposed project includes: 

The proposed project includes: 
  • Install new underground 69 kV circuit between Walnut Substation and Blount Substation 
  • Project will utilize existing vacant 8″ underground pipe facilities for majority of circuit path
  • Terminate new 69 kV line into existing line terminal at Walnut GIS Substation 
  • Create new line 69 kV line terminal at Blount Substation 

The target in-service date of this project is December 2030. A Certificate of Authority (CA) application is expected to be submitted to the PSCW in for this project. The project has been submitted to MISO MTEP27 as Target Appendix A. 

Racine County Distribution Interconnection and Western Feed Projects  

The Racine County Distribution Interconnection Projects consists of several new 138-kV transmission-to-distribution interconnection substations within the Electronics and Information Technology Manufacturing (EITM) zone in the village of Mount Pleasant to serve a large new load addition in southeast Wisconsin.  

These projects include:  
  • Nimbus Substation – New 138-kV breaker-and-a-half interconnection substation. 
  • Stratus Substation – New 138-kV breaker-and-a-half interconnection substation.   
  • Jupiter Substation – New 345/138-kV breaker-and-a-half interconnection substation with 4 – 500 MVA 345/138-kV transformers, +/- 350 Mvar STATCOM, and 138-kV capacitor banks.  
  • Cosmos Substation – New 345/138-kV breaker-and-a-half interconnection substation with 4 – 500 MVA 345/138-kV transformers, and 138-kV capacitor banks.  
  • Mount Pleasant Substation – Expand 345-kV and 138-kV breaker-and-a-half buses to interconnect new transmission lines, additional 500 MVA 345/138-kV transformer, +/- 350 Mvar STATCOM, and capacitor banks.  
    • Construct a new 138-kV double circuit line between the Mount Pleasant, Nimbus, and Stratus substations.  
  • The Racine County Western Feed transmission line scope includes:   
    • Construct two new 345-kV double circuit lines from the existing Arcadian – Pleasant Prairie/Arcadian – Paris 345-kV double circuit line to loop in and out of the Jupiter and Cosmos substations.  
    • Construct a new 345-kV line between the Jupiter, Mount Pleasant, and Cosmos substations.  

The Nimbus Substation was energized in March 2025.  The remainder of the projects are scheduled to be placed in-service through 2028. The CPCN application for the Racine County Western Feed Project was approved by the PSCW in May 2025.  These projects have been approved either through MISO’s EPR or MTEP25 plan.  

Elm Road – Racine 345 kV Project 

The Elm Road – Racine project will add 345 kV infrastructure between Elm Road and Racine Substations and the project 1) will address reliability issues stemming from nearby large load additions 2) is a required network upgrade to address limitations in MISOS’s DPP 2020 Cycle and 3) is included in MISO’s LRTP Tranche 2.1 portfolio as a subset of Project 29. 

The project includes: 
  • Elm Road Substation: Terminate the new line on the existing rung on the 345 kV breaker-and-a-half configuration.   
  • Racine Substation: Expand the 345 kV ring bus to a breaker-and-a-half configuration to provide a new termination point for the new line.   
  • Construct a new Elm Road – Racine 345 kV line on new ROW from the Elm Road Substation to the intersection with the Oak Creek to Racine 138 kV line (812), ~3.7 miles.  
  • Convert a portion of the Oak Creek – Racine 138 kV line (812) to 345 kV, ~9 miles. Retire the remaining portion of the line. Re-terminate the converted line into the Racine 345 kV bus. 

The target in-service date is April 2028. The CPCN application for the Elm Road – Racine Project was approved by the PSCW in September 2026. The project has been approved in MTEP24 Appendix A as a subset of MISO’s LRTP Project 29.  

Western UP Reliability Project 

The Western UP Reliability Project consists of 69 kV line rebuilds and a new 138 kV path from the Eagle River, WI area to the Twin Lakes, MI area near Baraga and Houghton, MI. This project will address existing reliability and asset renewal needs and prepare the Central and Western UP for future generation changes and load growth. 

The project includes: 
  • Lakota Rd. – Winona new 138 kV line double circuit with Conover – Mass and Mass – Winona 69 kV lines. 
  • Rebuild the Conover – Mass – Winona 69 kV lines to double circuit 138/69 kV from Lakota Rd to Winona 
  • Lakota Rd Substation – new 138 kV line terminal. 
  • Winona Substation – expand existing 138 kV bus. 
  • Watersmeet Substation-install line breakers 

The target in-service date is March 2031.  This is a proposed project currently listed in MTEP26 target appendix A.  A CA filing for the portion of scope in Wisconsin will be submitted in 2027.  

Nassau Blvd. 345-kV Generator Interconnection Substation 
The project includes: 
  • Facilitates the interconnection of 1,200 MW of solar generation at this location through three interconnection requests 
  • Taps the existing Rocky Run–Werner West 345-kV line and constructs a four-breaker 345-kV ring bus 

The target in-service date for this project is February 2028. A Certificate of Authority (CA) application was approved in March 2026, and the project has been submitted to MISO for inclusion in the MTEP27 Target Appendix A.