2025

10-Year
Assessment

Southeast Wisconsin
Zone 5

Transmission system limitations in Zone 5

A significant transmission system performance challenge in Zone 5 involves heavy energy market flows through the zone, resulting in potential high post-contingency line loadings.

Electricity usage

Peak electric demand typically occurs during the summer months. Large industrial loads in the Milwaukee metropolitan area are among the largest electricity users in the zone.  In addition, there were multiple large load interconnection requests submitted that resulted in several T-D interconnection projects and network upgrades to reliably serve the load addition. 

Transmission projects in Zone 5

The most notable planned, proposed, and provisional network/asset renewal projects in Zone 5 are listed below along with their projected year of completion and the factors driving the need for the projects. 

Zone 5 includes the counties of:
  • Kenosha , Wis.
  • Milwaukee , Wis.
  • Ozaukee , Wis.
  • Racine , Wis.
  • Washington , Wis.
  • Waukesha , Wis.

Zone 5 Planned Projects

Project DescriptionProject #In-service yearNeed driverRegulatory Update
Oak Creek, Racine SS and Remote Ends, Control Buildings and Relaying Asset Renewal12026Condition and PerformanceCA Approved in 2023
Elm Road Generation POI Relocation Project22026G-T InterconnectionCA Approved in 2025
Racine County Distribution Interconection and Western Feed Projects32025-2028T-D InterconnectionCPCN Approved in 2025
Everett GIS Asset Renewal42027Condition and PerformanceCA Approved in 2024
Mill Road – Granville Project52027ReliabilityCPCN Approved in 2025
Lincoln – 43rd Street Terminal 138 kV (5053), Replace with double circuit duct bank and XLPE cable62027Condition and PerformanceN/A
WisDOT I-94 Stadium Group of Projects92028Condition and PerformanceN/A

Zone 5 Proposed Projects

Project DescriptionProject #In-service yearNeed driverRegulatory Update
Ozaukee County DIC, New Substations72027T-D InterconnectionCPCN filed in 2025
North Saukville SS, DIC, New Substation82027T-D InterconnectionCA Targeted filing 2026

Zone 5 Provisional Projects

Project DescriptionProject #In-service yearNeed driverRegulatory Update
Harbor - Russel Terminal 138 kV (893K11), Replace Underground Cable102029Condition and PerformanceFiling Requirement TBD
Racine - St. Rita 138 kV (8531), Rebuild112030Reliability, Condition and PerformanceFiling Requirement TBD
Mukwonago – University 138 kV (UNIG52), Rebuild122031Condition and PerformanceFiling Requirement TBD