2025

10-Year
Assessment

Long Range Transmission Plan

The Midcontinent Independent System Operator (MISO), in shared responsibility with utilities and states, is leading the Long Range Transmission Planning (LRTP) effort.  

The goal of MISO’s LRTP projects is to ensure reliability, integrate the different operating characteristics of new generation resources and increase the resiliency of the grid in the face of severe weather events.  

The LRTP efforts have been broken into up to four tranches. The first tranche was unanimously approved by the MISO Board of Directors in July 2022. The estimated cost of LRTP Tranche 1 Portfolio is $10.3 billion. 

As part of the Tranche 1 portfolio, ATC is collaborating with Xcel Energy on multiple projects. ATC is the leading the development of LRTP Tranche 1 Project 6, which we call the Grid Forward Central Wisconsin Project. This project includes a rebuild of approximately 160 miles of existing power lines to add a new, approximately 200-mile, 345,000-volt power line and a substation expansion near Arpin, Wisconsin. ATC filed an application with the Public Service Commission of Wisconsin for the project in July 2024.  

The second phase of the LRTP portfolios, called Tranche 2.1, was approved by MISO in December 2024. ATC participated in the identification of potential projects that will reinforce our system to address current and anticipated needs and benefit energy consumers regionally and in our service area. 24 facilities in the Tranche 2.1 project list are designated as ‘Competitive Transmission Facilities’.  Those 24 facilities are grouped in 7 Competitive Transmission Projects, including 3 in the traditional ATC footprint. MISO is currently accepting requests for proposals (RFPs), reviewing submitted RFPs, and awarding projects to Selected Developers. 

LRTP Tranche 1 Project in ATC Footprint
IDProject NamePredominate kVTargeted ISDEst. Cost ($M, 2022)
Tremval – Eau Claire – Jump River 345 2028 $505 
Tremval – Rocky Run - Columbia 345 2029 $1,050 
LRTP Tranche 2.1 Project in ATC Footprint
IDProject Name Predominate kV Targeted ISD Est. Cost ($M, 2024) 
26 North Rochester – Columbia 765 2034 $1,924 
27 Rocky Run – Werner West – North Appleton 345 2032 $212 
28 South Fond du Lac – Rockdale – Big Bend – Sugar Creek – Kittyhawk 345 2033 $1,102 
29 Bluemond – Arcadian – Waukesha – Elm Road – Racine 345 2032 $731 
30 Columbia – Sugar Creek 765 2034 $743 
31 Sugar Creek - Collins 765 2034 $733 
Projects 26, 28, 30 are included in the MISO Competitive Transmission Project List

The most current information on the Long Range Transmission Plan can be found on MISO’s Long Range Transmission Planning Page. 

Grid Forward – Central Wisconsin Project 

The Grid Forward – Central Wisconsin Project is included in ATC’s portion of the Midcontinent Independent System Operator’s LRTP Tranche 1 portfolio. The project is needed to relieve constraints on the electric grid, improve reliability and provide access to lower-cost energy including renewable generation. ATC and Northern States Power Company, a subsidiary of Xcel Energy, are jointly proposing the project, which crosses 10 counties in central Wisconsin. 

The project includes: 

  • Rebuilding about 175 miles of existing power lines to support the construction of a new, approximately 200-mile, 345-kV power line from the Tremval Substation in Trempealeau County to the Arpin Substation in Wood County and from the Arpin Substation to the Columbia Substation in Columbia County. 

A Certificate of Public Convenience and Necessity (CPCN) application was submitted to the Public Service Commission of Wisconsin in July 2024. The in-service date is anticipated to be in 2030.