2026

10-Year
Assessment

Generation interconnections

The size and location of new or expanded power plants can have significant impacts on the transmission system. These impacts are largely evaluated in MISO Definitive Planning Phase (DPP) process.  Information on the status, as of October 17, 2026, of generation requests in the ATC portion of the MISO generation interconnection queue is provided in this section. There continues to be significant activity in ATC’s footprint, ranging from newly proposed generation projects to cancellation of previously proposed generation projects. 

There are two key aspects in determining the total impacts a proposed new generator may have on the transmission system: 

  • impacts of interconnecting the new generator to the transmission system and 
  • impacts of using the transmission system to deliver power from the new generator. 

As described in MISO’s Attachment X process, a generator interconnection study is performed in three phases which are all within the Definitive Planning Phase (DPP): System Impact Study (Phase 1, 2 and 3), Interconnection Customer Interconnection Facilities Study (Phase 2 and 3), and Network Upgrade Facilities Study which begins after the System Impact Study is completed in Phase 3.  

The System Impact Study includes a determination of whether the proposed generator and other nearby generators will remain connected to the system under various disturbance situations, such as line trips and equipment failures and includes a fault duty analysis to determine whether existing system equipment can accommodate the increased short circuit fault duty caused by the new generator. Additionally, the System Impact Study will identify solutions for any thermal, stability or fault duty deficiencies. 

Delivery impacts are assessed during the DPP portion of the interconnection study process using the MISO deliverability methodology, which determines whether the output of a new generator is deliverable to the MISO energy market and to what percent if not wholly deliverable. Whatever portion of the new generator that is deliverable may then be used as a Network Resource by Network Customers through MISO’s Module E Resource Adequacy procedures. 

The Interconnection Customer Interconnection Facilities Study is conducted in Phase 2 and 3. It specifies and estimates the time and cost of the equipment, engineering, procurement, and construction of the interconnection facility upgrades identified in the earlier interconnection studies. 

The Network Upgrade Facilities Study is conducted after Phase 3. It specifies and estimates the time and cost of the equipment, engineering, procurement and construction of the network system upgrades identified in the earlier interconnection studies. 

In addition to the DPP process, new resources could also be studied and approved through MISO Replacement process, MISO Surplus process, or the newly established MISO Expedited Resource Addition Study (ERAS) process. These are standalone processes and do not comprise multiple phases. 

  • Generator Replacement Study: Generator replacement interconnection is a process that allows new generators to connect to the electric grid at the same point where an existing one is planned to be retired. This is a faster and cost effective alternative to the standard interconnection queue because it leverages the existing infrastructure, leading to a quicker transition to new energy sources with fewer delays and lower costs.  
  • Surplus Study: The MISO surplus study process enables a new or hybrid generator to share an existing generator’s interconnection rights at the same point of interconnection (POI), thereby avoiding the need for new network upgrades and securing a faster interconnection. 
  • Expedited Resource Addition Study (ERAS): ERAS is a temporary and accelerated process established by MISO in 2025 to speed up the interconnection of new, urgently needed generation projects. This fast-track process is designed to address reliability and resource adequacy concerns by creating an alternative to the standard, often lengthy, interconnection study queues. 

The results of the interconnection studies are needed to develop a comprehensive picture of the transmission facilities that will be required for a proposed generator. Only transmission facilities that result from generators with a signed Interconnection Agreement are included in the 10-Year Assessment models. 

The first portion of the below section provides the status of the generation queue within ATC’s service territory. The second portion of this section describes proposed generation projects for which final interconnection studies have been completed. The third portion of this section describes some of the implications associated with interconnecting generation at various locations within ATC’s service territory. 

ATC Portion of MISO Generation Queue

Over the last ten years (October 2016 through October 2026), twenty eight (28) new generators have gone into service and five uprates or replacements to existing generators have been completed, totaling over 3,633 MW. These generators are included in Table PR-26. 

Table PR-26: Generator Requests From Past Ten Years Now In-Service

In-Service DateQueue Number and NameProject Capacity (MW)
2017-04-29J557 (Garden Corners solar)0.90
2017-05-01J384 (Christiana uprate)21.00
2017-12-01J395 (Quilt Block Wind Farm)98.00
2019-03-31J703 (Kuester)131.70
2019-03-31J704 (Mihm)56.50
2019-10-28J831 (Port Washington uprate)40.00
2020-05-14J390 & J760 (West Riverside)732.00
2020-11-02J886 (Two Creek Solar)150.00
2021-09-13J505 Point Beach Solar Energy Center100.00
2021-12-01J870 Badger Hollow 1150.00
2022-01-07J928 (Garden Wind80.00
2022-06-02J1183 Garden Solar)1.35
2022-10-17J864 (Bear Creek Solar)50.00
2023-01-20J1188 (North Rock Solar)50.00
2023-01-20J986 (Wood County Solar)150.00
2023-04-04J855 (Red Barn Wind Farm)100.00
2023-07-07R1010 (Weston Rice)133.00
2023-12-23J871, Badger Hollow II150.00
2024-02-09J1000, Cassville Solar50.00
2024-02-09J1304, Paddock Solar65.00
2024-02-09J1305, Albany Solar50.00
2024-02-27J1002, Wautoma Solar99.00
2024-02-27J1003, Beaver Dam Solar50.00
2024-03-01J1171, Springfield Solar100.00
2024-04-12J1153, Onion River Solar150.00
2024-04-16J1154, Crawfish River Solar75.00
2024-05-29J947, Grant County Solar200.00
2024-12-11J878, Paris Solar200.00
2025-03-03J850, Darien Solar250.00
2025-06-01S1005, Paris BESS0.00
2025-06-01J1316, Paris Solar50.00
2026-03-03J1251, Solar100.00
Total3,633

Table PR-27 lists the proposed generators in the generation queue for our service territory as of October 17, 2026, who have not yet signed the Generator Interconnection Agreement (GIA). It is important to keep in mind that the status of queued projects changes often as projects enter and withdraw from the queue, sign generator interconnection agreements, and start construction. This table lists each proposed generation project and summarizes them by zone and MW amount. These proposed projects also are shown by the approximate location in Figure PR-9.

As shown, the total capacity of proposed generators in this portion of the queue is roughly 11.19 GW. Of this proposed capacity, natural gas fired units reflect 55.6 percent, wind 4.8 percent, solar 22.9 percent, and storage 16.7 percent, (see Figure PR-10). Of the proposed capacity, 17.43 percent is in Zone 1, 3.25 percent is in Zone 2, 39.45 percent is in Zone 3, 19.45 percent is in Zone 4, and 20.43 percent is in Zone 5. 

Table PR-27: Proposed Projects Active in the Generation Queue Being Studied as of October 17, 2026

ZoneQueue#CountyProject Capacity (MW)Interconnection Voltage (kV)Generator Technology and Fuel
1J3469Marathon100115WIND
1J3975Rusk416.5345SOLAR
1J4069Marathon169.93115SOLAR
1J2520ADAM200138SOLAR
1J2559Wood200345SOLAR
1J2609Waushara80138SOLAR
1J2870Sawyer243.6345SOLAR
1J2944Wood350345GAS
1J3204Clark190345WIND
Zone 1 Subtotal1,950
2J3800Baraga1.8138GAS
2J3756Marquette4.2138GAS
2J3827Mackinac160138SOLAR
2J4085Dickinson42138SOLAR
2J4169Dickinson5.99138SOLAR
2J2678Delta150138SOLAR
Zone 2 Subtotal364
3J3639Columbia250345WIND
3J3402Juneau200345STORAGE
3J4028Walworth324138GAS
3J4164Dane1203345GAS
3J4097Rock71.5345SOLAR
3J4101Jefferson71138SOLAR
3J4116Walworth950345GAS
3J1935Dane50138SOLAR
3J1943Columbia200345SOLAR
3J1993Columbia99345SOLAR
3J2423Columbia300345STORAGE
3J2429Dane5069SOLAR
3J2666Walworth100138SOLAR
3J2947Rock205138GAS
3J3152Green160138GAS
3J3156Rock60138GAS
3J3162Rock100138STORAGE
3R5066Columbia20138STORAGE
Zone 3 Subtotal4,414
4J3466Winnebago100138SOLAR
4J4014650345GAS
4J4115Fondu Du Lac525345GAS
4J2055Sheboygan100345SOLAR
4J2326Outagamie150345STORAGE
4J3151Sheboygan150345GAS
4J3155Winnebago150138GAS
4J3160Fond du Lac100345STORAGE
4J2055_RSheboygan100345STORAGE
4E0038Winnebago150138GAS
Zone 4 Subtotal2,175
5J3785Kenosha200345STORAGE
5J3784Ozaukee200345STORAGE
5J3936Kenosha132.3138GAS
5J4165Kenosha1203345GAS
5J1895Kenosha200138STORAGE
5J2891Kenosha50138SOLAR
5J3006Milwaukee300345STORAGE
Zone 5 Subtotal2,285
Grand Total11,188

Table PR-28: Requests Previously in the Generation Queue Which Have been Withdrawn/Removed between June 1, 2025, and October 17, 2026. 

ZoneQueue#CountyProject Capacity (MW)Interconnection Voltage (kV)Generator Technology and FuelDate Withdrawn
1J2335Portage200.00115STORAGE2025-07-29
1J2345Marathon150.00345WIND2025-07-29
1J2365Portage160.00345STORAGE2025-07-29
1J2366Portage160.00345SOLAR2025-07-29
1J2439Marathon50.00345STORAGE2025-07-29
1J2557Wood100.00345STORAGE2025-07-29
1J2833Wood40.0069HYBRID2025-07-29
1J2277Portage0.00138STORAGE2025-09-25
Zone 1 Subtotal860
2J2354Marinette65.0069STORAGE2025-07-29
2J3638Dickinson50.00138STORAGE2025-09-30
2J3641Dickinson100.00138SOLAR2025-09-30
2J3642Dickinson60.00138SOLAR2025-09-30
2J3281Marquette170.00138WIND2025-12-23
Zone 2 Subtotal445
3J2324Winnebago35.0069HYBRID2025-07-29
3R1060Green95.00138GAS2025-10-31
Zone 3 Subtotal130
4J2537Shawano100.00345STORAGE2025-07-29
4J2544Shawano95.00345SOLAR2025-07-29
4J2834Fond du Lac50.0069HYBRID2025-07-29
4J3161Sheboygan100.00138STORAGE2025-07-29
4R1014Sheboygan100.80345STORAGE2025-07-30
4R1015Sheboygan303.50345STORAGE2025-07-30
4J2148Outagamie150.00138SOLAR2025-11-15
4J2211Brown200.00138STORAGE2025-11-15
4J3927Sheboygan150.00138SOLAR2025-12-23
4J1101Manitowoc20.00138STORAGE2026-02-24
Zone 4 Subtotal1,269
5J3330Kenosha705.00345GAS2025-09-11
5J3332Calumet150.00345WIND2025-09-30
5J1492Racine200.00138STORAGE2026-01-05
5J4171Racine300.00138STORAGE2026-01-05
Zone 5 Subtotal1,355
Grand Total4,059

Table PR-29: Active Projects in the Generator Queue in Construction or waiting construction as of October 17, 2026. It includes projects with signed GIA. 

ZoneQueue#CountyProject Capacity (MW)Interconnection Voltage (kV)Generator Technology and Fuel
1J732Douglas562345GAS
1J1502Juneau225345SOLAR
1J1508Marathon98.9115WIND
1J1573Portage250115SOLAR
1J1751Wood150.5138SOLAR
1J1752Portage148.1138SOLAR
1J2099Portage399.03345SOLAR
1J2107Portage399.03345SOLAR
1J2185Portage399.03345SOLAR
1J2193Waushara100138HYBRID
Zone 1 Subtotal2,732
2J1750Marquette149.7138SOLAR
2J1814Dickinson22.5138SOLAR
2J2029Marquette62.5138SOLAR
2J2316Dickinson77.5138SOLAR
Zone 2 Subtotal312
3J818Jefferson149138SOLAR
3J1214Dane300345SOLAR
3J1326Dane75345STORAGE
3J1374Grant67.2138WIND
3J1377Rock98.56345SOLAR
3J1410Dane300345SOLAR
3J1411Dane75345STORAGE
3J1460Rock200138SOLAR
3J1483Iowa99345WIND
3J1629Columbia200345SOLAR
3J1706Green100138SOLAR
3J1732Columbia98.4138SOLAR
3J1746Columbia150138SOLAR
3J1773Iowa, Lafayette300345WIND
3J1779Dane200345HYBRID
3J1781Iowa, Lafayette300345WIND
3J1824Columbia67138SOLAR
3J1931Iowa40345WIND
3J2304Columbia400345STORAGE
Zone 3 Subtotal3,219
4J1513Waupaca300138SOLAR
4J1615Oconto150138SOLAR
4J1745Winnebago100138SOLAR
4J1793Sheboygan75138SOLAR
4R1049Sheboygan300345Coal
4R5061Sheboygan100345Coal
4E0016Calumet1203345GAS
4E0037Sheboygan150345GAS
Zone 4 Subtotal2,378
5J1778Kenosha100138SOLAR
5J1934Kenosha150138STORAGE
5R1053Milwaukee1138.5345GAS
5E0012Kenosha1168345GAS
Zone 5 Subtotal2,557
Grand Total11,198
Includes projects with signed GIA.

Link to publicly posted MISO generation queue

Implications of generation development

From a transmission perspective, the ability of the transmission system to accommodate new generation is a function of stability, power flow and short circuit analyses. For certain generation technologies, harmonics, fast control interactions and voltage fluctuations may need to be considered as well. In most instances, new generation will require certain transmission system reinforcements to interconnect and deliver the generation output. In a few specific instances, new generation can be beneficial to the transmission system, even deferring or eliminating the need for transmission reinforcements that would be necessary absent the new generation. The ability of generation to defer or eliminate the need for transmission reinforcements also can be a function of the generation location, number of generators, and/or expected generator capacity factor. 

In this section, a general zone-by-zone evaluation of the likelihood of needing or deferring transmission reinforcements for various generator locations is provided. The purpose of these evaluations is to provide a cursory indication to the generation market of the likely magnitude of the impact and the transmission reinforcements that would likely be needed by general location. 

Zone 1

In Zone 1, about 17.43 percent (~1,950 MW, Table PR-27) of the proposed generation is located near the 345-kV infrastructure. Based on studies that ATC has conducted for proposed generation interconnections to date some transmission reinforcements are likely to be required for any significant generation development. The extent and nature of the reinforcements largely would be a function of where the power from the generation is to be delivered.  

The transmission infrastructure in the central portion of Zone 1 includes five 345 kV lines (Gardner Park – Highway 22, Gardner Park – Stone Lake, Gardner Park – Rocky Run, Rocky Run – Arpin, and Rocky Run – Werner West) and two 345 kV tie lines to neighboring entities. These lines significantly strengthen the Weston area, bringing much needed support to the area for both stability and thermal considerations. Furthermore, the new lines included in the MISO Long Range Transmission plan (LRTP) significantly strengthen this area.  

The infrastructure in the southern portion of Zone 1 consists of several 69 kV and 138 kV lines. The existing infrastructure in this portion of Zone 1 is not suitable for significant generation development. 

Three Zone 1 generator projects went in service or are in construction in the last five years, October 2021 to October 2026. 

Zone 1 Generators In Construction or In Service

RequestSize (MW)TypeCountyStateStatus
J100299SolarWausharaWIIn Service
J986150SolarWoodWIIn Service
R1010133Natural GasMarathonWIIn Service
J732527.8Natural GasDouglasWIIn Construction
J1502225SolarJuneauWIIn Construction
J150898.9WindMarathonWIIn Construction
J1573250SolarPortageWIIn Construction
J1751150.5SolarWoodWIIn Construction
J1752148.1SolarPortageWIIn Construction
J2099399.03SolarPortageWIIn Construction
J2107399.03SolarPortageWIIn Construction
J2185399.03SolarPortageWIIn Construction
J2193100HybridWausharaWIIn Construction
Zone 1 generators in construction or in service in the last 5 years.

Zone 2

ATC has seen substantial interest in siting generators in the Upper Peninsula of Michigan. In Zone 2, about 3.25 percent (~364 MW, Table PR-27) of the active generation in the queue is at various locations throughout the zone. One of the major challenges proposed generation in the Upper Peninsula will face is the limited transmission infrastructure to interconnect and deliver the energy produced by these generators. Since the Upper Peninsula transmission grid was primarily designed to serve local load, transmission upgrades may be required to accommodate these proposed plants. 

There are areas in Zone 2, which currently or will eventually need transmission reinforcements where smaller generation projects could be beneficial in terms of deferring transmission expenditures. The allowable capacity and potential impacts of such generation would depend on location. Impacts like thermal, stability and fault duties would need to be evaluated through the DPP process. 

The following table lists Zone 2 generator projects in service or in construction in the last five years, October 21 to October 2026. 

Zone 2 Generators In Construction or In Service

RequestSize (MW)TypeCountyStateStatus
J92880WindDelta CountyMIIn Service
J11831.4SolarDelta CountyMIIn Service
J1251100SolarMarquette CountyMIIn Service
J1750149.7SolarMarquette CountyMIIn Construction
J181422.5SolarDickinsonMIIn Construction
J202962.5SolarMarquetteMIIn Construction
J231677.5SolarDickinsonMIIn Construction
Zone 2 generators in construction or in service in the last five years.

Zone 3

In Zone 3, about 39.45 percent (~4,414 MW, Table PR-27) of the active generation in the queue is at various locations throughout the zone. In recent cycles, there are more proposals in Dane and Columbia Counties and along the Cardinal-Hickory Creek Transmission Line Project corridor (especially in Iowa and Grant Counties). Furthermore, the new line, terminating at Columbia 345-kV Substation, included MISO Long Range Transmission plan (LRTP) will significantly strengthen the area. Furthermore, the new line, terminating at Columbia 345-kV Substation, included MISO Long Range Transmission plan (LRTP) will significantly strengthen the area. 

Similarly, the southeast portion of Zone 3 continues to be an attractive location for siting generation. However, generation studies completed in the southwest corner of the state have demonstrated that siting large amounts of generation in rural areas may require substantial upgrades to the transmission system to ensure reliable operation. 

The following table lists Zone 3 generator projects in service or in construction in the last five years, October 2021 to October 2026. 

Zone 3 Generators In Construction or In Service

RequestSize (MW)TypeCountyStateStatus
J870200SolarIowaWIIn Service
J871100SolarIowaWIIn Service
J947200SolarGrantWIIn Service
J100050SolarGrantWIIn Service
J100350SolarDodgeWIIn Service
J115475SolarJeffersonWIIn Service
J118850SolarRockWIIn Service
J130465SolarRockWIIn Service
J130549.9SolarGreenWIIn Service
J818149SolarJeffersonWIIn Construction
J1214300SolarDaneWIIn Construction
J132675StorageDaneWIIn Construction
J137467.2WindGrantWIIn Construction
J137798.56SolarRockWIIn Construction
J1410300SolarDaneWIIn Construction
J141175StorageDaneWIIn Construction
J1460200HybridRockWIIn Construction
J148399WindIowaWIIn Construction
J1629200SolarColumbiaWIIn Construction
J1706100SolarGreenWIIn Construction
J173298.4SolarColumbiaWIIn Construction
J1746150SolarColumbiaWIIn Construction
J1773300WindIowa, LafayetteWIIn Construction
J1779200HybridDaneWIIn Construction
J1781300WindIowa, LafayetteWIIn Construction
J182467SolarColumbiaWIIn Construction
J193140WindIowaWIIn Construction
J2304400StorageColumbiaWIIn Construction
Zone 3 generators in construction or in service in the last five years

Zone 4

In Zone 4, about 19.44 percent (~2,175 MW, Table PR-27) of the active generation in the queue is at various locations throughout the zone. . Given the nature of the issues in Zone 4, it is unlikely that new generation will significantly alter the need for the major transmission reinforcements contemplated in that zone.  In recent generation studies, more stress on the 138-kV paths from Pulliam to Highway V and North Appleton – Lost Dauphin is observed and may need substantial reinforcements if the new generation projects move forward. 

One area where generation could defer the need for transmission reinforcements is in Door County, provided such generation is small-scale and appropriately located. Currently, the northern portion of the county is served radially and electric service is subject to interruption for the loss of the single 69 kV line serving the area. The voltage profile in Door County is projected to precipitate the need for reinforcements in the future. Small-scale generation potentially could defer some of these reinforcements. 

The following table lists Zone 4 generator projects in service or in construction in the last five years, October 2021 to October 2026. 

Zone 4 Generators In Construction or In Service

RequestSize (MW)TypeCountyStateStatus
J1153150SolarSheboygan Wis.WIIn Service
J1171100SolarDodgeWIIn Service
J110120StorageManitowocWIIn Construction
J1513300SolarWaupacaWIIn Construction
J1615150SolarOcontoWIIn Construction
J1745100SolarWinnebagoWIIn Construction
J179375SolarSheboyganWIIn Construction
R1049300CoalSheboyganWIIn Construction
R5061100CoalSheboyganWIIn Construction
E00161203GasCalumetWIIn Construction
E0037150GasSheboyganWIIn Construction
Zone 4 generators in construction or in service in the last five years.

Zone 5

In Zone 5, about 20.43 percent (~2,285 MW, Table PR-27) of the active generation in the queue is at various locations throughout the zone.  The developments related to Microsoft’s large data center load in Southeast Wisconsin are expected to get some reinforcement to the local transmission capacity and that may make it attractive for new generators to locate there.  

The following table lists Zone 5 generator projects in service or in construction in the last five years, October 2021 to October 2026. 

RequestSize (MW)TypeCounty,StateStatus
J878200SolarKenoshaWIIn Service
J131650StorageKenoshaWIIn Service
J1778100SolarKenoshaWIIn Construction
J1934150StorageKenoshaWIIn Construction
R10531138.5GasMilwaukeeWIIn Construction
E00121168GasKenoshaWIIn Construction