ZONES & STUDY RESULTS
    Introduction
Zone 1
Overview
2009 analysis
2013 analysis
2018 analysis
2023 analysis
Zone 2
Zone 3
Zone 4
Zone 5
Reactive analysis
Multiple outages
Planned reinforcements
System stability
All project models
Load Sensitivity
  RELATED RESOURCES
 
Table ZS-1 -- Constraints 2009 (266k pdf)
Table ZS-2 -- Constraints 2013 (414k pdf)
LOAD SENSITIVITY PDF of Current Page
 

The analysis that we perform for each 10-Year Assessment is based on power flow analysis using specific load forecast assumptions. The load forecast assumes there is some probability of exceeding the load forecast on the peak day. A traditional practice for generation and transmission planning in Wisconsin has been to use a load forecast probability of 50 percent (also known as a 50/50 forecast). This means that there is a 50 percent chance that the actual system peak load will exceed the forecasted value in any given year or, to state it another way, it is expected that on the average the forecast will be exceeded once every two years. The problem with analysis based on the traditional method is that it does not indicate the reliability risk of the actual system peak exceeding the forecasted value. The question then is, what is the risk to reliable system operation in the ATC footprint if the forecast is exceeded and what, if anything, should be done to mitigate some or all of the risk?

 

One way to assess this risk is to increase the load forecast and determine whether or not ATC’s proposed projects can reliably serve this increased electricity usage. To accomplish this purpose, some utilities use a 90/10 forecast , as opposed to the 50/50 forecast. ATC has relied on its customers to provide the load forecasts for our analysis, so we currently do not have a 90/10 forecast available for the risk assessment in the 2008 Assessment. However, general discussions have found that a 5 percent increase in certain peak loads may be a reasonable assumption for a 90/10 versus a 50/50 forecast. Therefore, for the 2008 Assessment, ATC has used a 5 percent increase in certain peak loads as a proxy for the higher 90/10 forecast.

 

ATC applied a 5 percent increase to scalable peak hour loads in the power flow models representing the year 2013. In Zones 1, 3, 4 and 5, ATC found that the increased load did not have a significant impact on the need for projects. While we did not see that he increased load had a major impact on voltages, we did see areas where voltage is expected to be marginal for the 5% increased forecast. These voltages will need to be considered more carefully to determine if any mitigation should be considered for higher than expected load.

 

In Zone 2, ATC found that the increased load did have a significant impact on the need for proposed projects. For the outage of either the Hiawatha-Engadine 69-kV line or the Engadine-Newberry 69-kV line, it is projected that the Eastern U.P. will experience voltage collapse under the 90/10 scenario. ATC has commenced an Energy Collaborative discussion in Zone 2 to identify reasonable futures and drivers that should be considered in developing appropriate plans for Zone 2. As part of this effort, we expect to define what transmission reinforcements will be appropriate to address these potential issues. Table ZS-2 compares the results of the 50/50 and proxy 90/10 analyses for 2013 for Zones 1-5.

 

We saw some additional areas where previously marginal voltage worsened and/or thermal overloads were aggravated as loads increased. In Zone 3, the in-service dates of at least three projects become more critical if loads are higher than expected:

  • Bass Creek 138/69-kV transformer and Bass Creek-Town Line Road 138-kV rebuild (2013),
  • Loop Nine Springs-Pflaum 69-kV line into Femrite (2013), and
  • Horicon (Hubbard)-East Beaver Dam 138-kV line (2014).

 

At this time, ATC is not proposing to advance any project timings to anticipate higher loads or load growth. However, we will continue to evaluate these conditions in future Assessments.

 

 

A 90/10 forecast generally means that there is a 90 percent chance that the load will be less than the forecasted value. Thus, a load based on a 90/10 forecast load would be higher than a load based on a 50/50 forecast where there is only a 50 percent chance that the load will be less than the forecasted value

Scalable means that these loads follow some predictable load cycle pattern throughout the year that may or may be sensitive to extreme weather conditions.



 
Copyright 2008 American Transmission Company. All Rights Reserved