PROJECTS (updated Sept 2008)
    Classifications
Completed since 2007
New in 2008
Under construction
Approved
Pending approval
Costs
Generation Interconnections
T-D Interconnections
  RELATED RESOURCES
 
Figure PR-6 -- Number of projects 2001-2006 (151k pdf)
Table PR-1 --  Projects in service since 2005 Update (104k pdf)
Table PR-2 -- 2006 Projects (149k pdf)
Table PR-3 -- 2007 Projects (225k pdf)
Table PR-4 -- 2008 Projects (279k pdf)
Table PR-5 -- 2009 Projects (216k pdf)
Table PR-6 -- 2010 Projects (179k pdf)
Table PR-7 -- 2011 Projects (136k pdf)
Table PR-8 -- 2012 Projects (151k pdf)
Table PR-9 -- 2013 Projects (153k pdf)
Table PR-10 -- 2014 Projects (162k pdf)
Table PR-11 -- 2015 Projects (126k pdf)
Table PR-12 -- 2016 Projects (126k pdf)
Table PR-13 -- Zone 1 Projects (205k pdf)
Table PR-14 -- Zone 2 Projects (223k pdf)

Table PR-15 -- Zone 3 Projects (339k pdf)

Table PR-16 -- Zone 4 Projects (225k pdf)
Table PR-17 -- Zone 5 Projects (174k pdf)
Table PR-18 -- New Right-of-way Projects (66k pdf)
Table PR-19 -- Rebuild Projects on Existing Right-of-way (71k pdf)
Table PR-20 -- New Substation and Transformer Projects (66k pdf)
Table PR-21 -- Substation Equipment Projects (73k pdf)
Table PR-22 -- Alternate Solutions to Projects (68k pdf)
Table PR-23 -- Summary of Cancelled, Deferred or New Projects (247k pdf)
Table PR-24 -- Maintenance Projects >$0.5 million (133k pdf)
Table PR-25 -- Projects in Design or Construction (93k pdf)
Table PR-26 -- Approved Projects (85k pdf)
Table PR-27 -- Projects Pending Approval (88k pdf)
CLASSIFICATIONS PDF of Current Page
 

CLICK HERE FOR UPDATED 2007 INFORMATION

In our 10-Year Assessments and Updates, projects are identified that address reliability issues, transmission service issues, generation interconnections or some distribution interconnections, or a combination of two or more of the above. In general, these projects address system performance issues per the governing system planning criteria. We have numerous other projects under way or under evaluation that address other issues, including obsolete substation equipment, line facilities in poor condition, line relocations and most distribution interconnections. The projects referenced in the project tables PR-2 through PR-27 include only those projects that address system performance issues.

 

To facilitate an understanding of the status of the various future projects, we classify projects into one of three possible categories – Planned, Proposed or Provisional. Each classification has specific criteria based on the status of the project as outlined below:

 

Planned projects:

  • ATC planning is complete;
  • if required, we have applied for regulatory approvals, which may be pending or have been issued;
  • project may be under construction or in construction planning phase; and
  • project typically is included in power flow models used to analyze transmission service requests.

Proposed projects:

  • ATC planning is not complete;
  • ATC has not yet pursued regulatory approvals;
  • project represents ATC’s preliminary preferred project alternatives from a system performance perspective; and
  • project typically is not included in power flow models used to analyze transmission service requests.

Provisional projects:

  • ATC planning is not complete;
  • ATC has not yet sought regulatory approvals;
  • project does not necessarily represent ATC’s preliminary preferred project alternative, but reflects a placeholder project designation; and
  • project is not included in power flow models used to analyze transmission service requests.

In the 2001-2006 10-Year Assessments and Updates, we identified or assumed responsibility for 591 projects that address system performance issues. Figure PR-6 illustrates the status of all Planned, Proposed, and Provisional projects from 2001-2006. Regarding Figure PR-6, it is worthwhile to note that:

  • ATC has completed 181 projects and another 14 are under construction. Notable projects most recently completed are listed in Table PR-1. Projects under construction range from capacitor bank installations to the Arrowhead-Weston/Gardner Park transmission line project.
  • 85 projects have been replaced with alternate project solutions. It is not unusual that the status of certain projects will change or evolve since customer needs and uses of the transmission system continually are changing.
  • ATC canceled 112 projects that were identified in previous Assessment reports. Due to changing needs and up-to-date information, these projects were determined unnecessary. Most of these projects were relatively minor projects, involving only replacement of equipment at existing substations.
  • 199 future projects are in various stages of evaluation or development (Planned, Proposed or Provisional).
 
Copyright 2008 American Transmission Company. All Rights Reserved